Calculation of Cement Mortar|Cement Mortar Calculation in Brick Masonry

Photo of author
Written By Sourabh Negi

I cover structural design, construction technology and building materials.

Calculation of cement mortar is done to determine the quantity of cement and sand for different ratios of the cement mortar. For instance, for the cement mortar ration 1:6, total 5.50 bags of cement and 1.14 cum of sand will be required.

Calculation of Cement Mortar

Let us calculate the volume of mterial required for 1 cum of mortar

Vol of dry mortar = 33% extra of wet mortar = 1+0.33×1 = 1.33 cum (considering 33% volume of voids)

Calculation of Cement Mortar 1:6

Volume of cement in cum = (1×1.33) / 7 = 0.19m3 Volume of 1 bag of cement = (Weight /Density) = 50 / 1440 = 0.0347 m3 No. of cement bags needed = 0.19 / 0.0347 = 5.48 bags.
Volume of sand = (6x 1.33) /7 = 1.14 m3

Calculation of Cement Mortar 1:5

Volume of cement in cum = (1×1.33) / 6 = 0.22m3 No. of cement bags needed = 0.22/ 0.0347 = 6.34 bags.
Volume of sand = (5x 1.33) /6 = 1.11 m3

Calculation of Cement Mortar 1:4

Volume of cement in cum = (1×1.33) / 5 = 0.27m3 No. of cement bags needed = 0.27/ 0.0347 = 7.78 bags.
Volume of sand = (4x 1.33) /5 = 1.06 m3

Calculation of Cement Mortar 1:3

Volume of cement in cum = (1×1.33) / 4 = 0.33 m3 No. of cement bags needed = 0.33/ 0.0347 = 9.51 bags.
Volume of sand = (3x 1.33) /4 = 1.00 m3

Calculation of Cement Mortar 1:2

Volume of cement in cum = (1×1.33) / 3 = 0.44 m3 No. of cement bags needed = 0.44/ 0.0347 = 12.68 bags.
Volume of sand = (2x 1.33) /3 = 0.89 m3

Calculation of Cement Mortar 1:1

Volume of cement in cum = (1×1.33) / 2 = 0.67 m3 No. of cement bags needed = 0.67/ 0.0347 = 19.31 bags.
Volume of sand = (1x 1.33) /2 = 0.67 m3

Cement Mortar RatioSumVolume of CementNo. of bags of CementVolume of Sand
Cement Mortar 1:61+6 = 7=(1×1.33)/7= 0.19 cum0.19/0.0347 =5.48 =(6×1.33)/7=1.14 cum
Cement Mortar 1:5 1+5 = 6 =(1×1.33)/6= 0.22 cum 0.22/0.0347 =6.34 =(5x 1.33 )/6=1.11 cum
Cement Mortar 1:4 1+4 = 5 =(1×1.33)/5= 0.27 cum 0.27/0.0347 =7.78 =(4x 1.33 )/5=1.06 cum
Cement Mortar 1:3 1+3 = 4 =(1×1.33)/4= 0.33 cum 0.33/0.0347 =9.51 =(3x 1.33 )/4=1.00 cum
Cement Mortar 1:21+2 = 3 =(1×1.33)/3= 0.44 cum 0.44/0.0347 =12.68 =(2x 1.33 )/3=0.89 cum
Cement Mortar 1:11+1 = 2 =(1×1.33)/2= 0.67 cum 0.67/0.0347 =19.31 =(1x 1.33 )/2=0.67 cum
Summary of Cement Mortar Calculation
Cement Mortar RatioNumber of Bags of CementThe volume of Sand in Cum The volume of Sand in Cubic foot
Cement Mortar 1:6 5.501.1440
Cement Mortar 1:5 61.1139
Cement Mortar 1:481.0637
Cement Mortar 1:3101.0035
Cement Mortar 1:2130.8931
Cement Mortar 1:119.500.6724
Qty. of Cement and Sand in 1 cum of Cement Mortar


Cement Mortar Calculation in Brick Masonry

Cement mortar calculation in brick masonry consists of determining the total quantity of mortar required per unit volume of brick Masonry. By knowing the quantity of mortar we can calculate the total quantity of cement and sand in the masonry.

Calculation of Cement Mortar in 10 cum of Brick Masonry

  • Size of standard Brick (with mortar) = 20 x10x10 (in cm).
  • Total Number of Brick required for 1 cum of brickwork = 1/(0.20×0.10×0.10) = 500 Nos.
  • Number of Bricks for 10 cum of brick masonry = 5000.
  • Volume of bricks without mortar = 5000x 0.19x 0.09x 0.09 = 7.7 cum.
  • Volume of mortar = total volume of brickwork – vol of bricks= 10-7.7 = 2.3 cum
  • add 10% wastage = 2.3 + 0.1×2.3 = 2.53 cum.
  • add 25% extra for dry mortar weight = 2.53+0.25×2.53 = 3.16 cum.

This is because the volume of dry mortar is always more than the volume of wet mortar. If you take 1 cum of dry mortar and add water to it for making mortar. The final volume will always be lower than the 1 cum. To account for this, 25% is added.

Now we have calculated that for 10 cum of brickwork approximately 3.16 cum of dry mortar is required.

Cement Mortar 1:6 Calculation in Brick Masonry

Volume of cement in cum = (1×3.16) / 7 = 0.45 m3
Volume of sand = 3.16 – 0.45 = 2.71 m3 or (6x 3.16) /7 = 2.71 m3
Volume of 1 bag of cement = (Weight /Density) = 50 / 1440 = 0.0347 m3
No. of cement bags needed = 0.45 / 0.0347 = 12.97 bags.

Cement Mortar 1:5 Calculation in Brick Masonry

Volume of cement in cum = (1×3.16) / 6 = 0.53 m3
Volume of sand = 3.16 – 0.53 = 2.63 m3 or (5x 3.16) /6 = 2.63 m3
No. of cement bags needed = 0.53 / 0.0347 = 15.27 bags.

Cement Mortar 1:4 Calculation in Brick Masonry

Volume of cement in cum = (1×3.16) / 5 = 0.63 m3
Volume of sand = 3.16 – 0.63 = 2.53 m3 or (4x 3.16) /5 = 2.53 m3
No. of cement bags needed = 0.63 / 0.0347 = 18.16 bags.

Cement Mortar 1:3 Calculation in Brick Masonry

Volume of cement in cum = (1×3.16) / 4 = 0.79 m3
Volume of sand = 3.16 – 0.79 = 2.37 m3 or (3x 3.16) /4 = 2.37 m3
No. of cement bags needed = 0.79 / 0.0347 = 22.77 bags.

Cement Mortar 1:2 Calculation in Brick Masonry

Volume of cement in cum = (1×3.16) / 3 = 1.05 m3
Volume of sand = 3.16 – 1.05 = 2.11 m3 or (2x 3.16) /3 = 2.11 m3
No. of cement bags needed = 1.05 / 0.0347 = 30.26 bags.

Cement Mortar 1:1 Calculation in Brick Masonry

Volume of cement in cum = (1×3.16) /2 = 1.58 m3
Volume of sand = 3.16 – 1.58 = 1.58 m3 or (1x 3.16) /2 = 1.58 m3
No. of cement bags needed = 1.58 / 0.0347 = 45.53 bags.

Summary

Cement Mortar RatioSumVolume of CementNo. of bags of CementVolume of Sand
Cement Mortar 1:61+6 = 7=(1×3.16)/7= 0.45 cum0.45/0.0347 =12.97 =(6×3.16)/7=2.71 cum
Cement Mortar 1:5 1+5 = 6 =(1×3.16)/6= 0.53 cum 0.53/0.0347 =15.27 =(5×3.16)/6=2.63 cum
Cement Mortar 1:4 1+4 = 5 =(1×3.16)/5= 0.63 cum 0.63/0.0347 =18.16 =(4×3.16)/5=2.53 cum
Cement Mortar 1:3 1+3 = 4 =(1×3.16)/4= 0.79 cum 0.79/0.0347 =22.77 =(3×3.16)/4=2.37 cum
Cement Mortar 1:21+2 = 3 =(1×3.16)/3= 1.05 cum 1.05/0.0347 =30.26 =(2×3.16)/3=2.11 cum
Cement Mortar 1:11+1 = 2 =(1×3.16)/2= 1.58 cum 1.58/0.0347 =1.30 =45.53 =(1×3.16)/2=1.58 cum C
Summary of Cement Mortar Calculation in Brick Masonry
Cement Mortar RatioNumber of Bags of CementVolume of Sand in Cum Volume of Sand in Cubic foot
Cement Mortar 1:6 132.7198
Cement Mortar 1:5 152.6393
Cement Mortar 1:4182.5389
Cement Mortar 1:3232.3784
Cement Mortar 1:2302.1175
Cement Mortar 1:1461.5856
meant

In above examples we have calculated the quantities of cement and sand in Cement Mortar and in Cement Brickwork. You can change the void content which I have taken for the calculation e.g. 33% for cement mortar. A similar example has been done by taking 60% void content by Theconstructor.org.