The rate analysis of brickwork involves working out the cost of materials like brick, sand, and cement and the cost of labour. The cost of material, as well as labour charges, varies from place to place. The availability of material and labour also affects the rates. In this article, we will learn to calculate the cost of brick walls.

Stepwise Calculation for Rate Analysis of Brickwork

Rate analysis is done to determine the probable cost of the work which is to be done. The Estimated cost helps in determining the capital requirement for the work. Rate Analysis of brickwork involved three Steps. First is determining the quantity of material like Bricks, Cement and Sand required. The Second Step is determining the rate and amount of labour required for brickwork.

Calculation of Material for 1 cum of Brickmasonry

In Brick masonry, the material required is Cement, Sand and Bricks. The quantity of these materials is required to be known beforehand. The process of calculation of material for 1 cum of brick masonry involves determining the quantity of cement in bags, the quantity of sand in cum and the number of bricks required.

Calculation of Bricks for 1 cum of Brickmasonry

The number of bricks depends on the size of the brick available. As per Indian Standard, the modular bricks have a size of 19 cm x 9cm x 9cm. Non-Modular bricks are available in different sizes. The choice of a particular size also depends on the location. Some States in India use different sizes compared to others. The most commonly used Non-Modular Bricks are 230x110x70 mm. As the thickness of and beam is usually kept 230 mm in India. Thus 230 mm length brick is commonly used.

No matter, what the size of brick is, you can always calculate the total number of bricks required for 1 cum of Brick Masonry. In the example shown below, I have calculated the total number of Standard size bricks required for 1 cum of Brickwork.

  • Standard Size of Bricks with Mortar = 20x10x10 cm (assuming 1 cm of mortar)
  • Number of Bricks in 1 Cum of Brickwork = 1/(0.2*0.1*0.1) =500 Nos.
  • You can also add approx 5% as wastage. Thus total bricks will be 500*1.05 = 525.
  • Likewise you can calculate the total bricks of sizes 230x110x110 mm, 230x110x70 mm, 230x110x30 mm.

Calculation of Mortar for 1 cum of Brickmasonry

  • The volume of 1 Brick without mortar = 0.19×0.09×0.09 =0.001539 (taking standard size brick as example)
  • Volume of Bricks in 1 cum of Brickwork = 500x 0.001539 = 0.7695
  • Volume of Mortar= 1-0.7695 = 0.2305 Cum
  • Add 25% extra for Dry volume of a mortar = 0.2305 Cu.m. x 1.25 = 0.288125 Cu.m.
  • Add 10% extra for wastage = 0.288125*1.10 =0.316 Cum
  • For 10 cum of Brickwork, quantity of mortar = 3.16 cum
  • Qantity of Cement and Sand for 10 Cum of Mortar is given below:-
Cement Mortar RatioSumVolume of CementNo. of bags of CementVolume of Sand
Cement Mortar 1:61+6 = 7=(1×3.16)/7= 0.45 cum0.45/0.0347 =12.97=(6×3.16)/7=2.71 cum
Cement Mortar 1:51+5 = 6=(1×3.16)/6= 0.53 cum0.53/0.0347 =15.27=(5×3.16)/6=2.63 cum
Cement Mortar 1:41+4 = 5=(1×3.16)/5= 0.63 cum0.63/0.0347 =18.16=(4×3.16)/5=2.53 cum
Cement Mortar 1:31+3 = 4=(1×3.16)/4= 0.79 cum0.79/0.0347 =22.77=(3×3.16)/4=2.37 cum
Cement Mortar 1:21+2 = 3=(1×3.16)/3= 1.05 cum1.05/0.0347 =30.26=(2×3.16)/3=2.11 cum
Cement Mortar 1:11+1 = 2=(1×3.16)/2= 1.58 cum1.58/0.0347 =1.30 =45.53=(1×3.16)/2=1.58 cum
Quantity of Cement and Sand in 10 Cum of Brickmasonry.

To learn how I calculated the volume of Cement and Sand please read this article Cement Mortar Calculation in Brick Masonry.

Calculation of Labour rate for Brickwork

Brickwork Labour rate per cum for Brickwork can be calculated by knowing the amount of work labor can do in a day. The day for labour is not 24 hours but the day term is referred to the working hours i.e. 8 hours. So 8 hours of work is counted as a day. The total labour requirement for 1 cum of brickwork is :

  • 1 Mason can do 1.25 Cum of Brickwork in a day.
    • For 1 cum of Brickwork, Mason required = 1/1.25 =0.8 Nos.
    • If two Masons i.e. 1st Class and 2nd Class are engaged, the amount of Mason required = 0.8/2 = 0.4 per day
  • 1 Coolie can do 0.7 Cum of Brickwork, for 1 cum of brickwork = 1/0.7 = 1.43 coolie will be required.
  • 1 Bishti can do 5 cum of Brickwork in superstructure. For 1 cum of Brickwork, no. of Bhishti = 1/5 = 0.20

Rate Analysis for Brickwork

Rate Analysis of 1 cum of BrickworkUnitQuantity RateAmount
MATERIAL FOR 1 CUM OF BRICKWORK
BricksNos.50052500
Cement for Mortar 1:4Bag1.82450819
Sand for Mortar 1:4 cum0.2531000253
LABOUR RATE FOR BRICKWORK Per CUM
Mason 1st Classday0.4750300
Mason 2nd Class day0.4750300
Coolieday1.43600858
Bhishtiday0.20600120
ScaffoldingLS50
Total5200
Add 1% Water Charges52
Total 5252
Add GST on (multiplying factor 0.1405)737.91
Total5989.91
Add 15% Contractor Profit and Overhead Charges898.49
Total6888.40
Add 1% Cess68.88
Total6957.28
Rate Analysis of Brickwork
Rate Analysis of Brickwork
Rate Analysis of Brickwork

So, the total cost of 1 cum of brickwork = 6957 INR.

The rate depends on a variety of factors, i.e. rate of Labour, Material, etc. Generally, the Rate of Brickwork varies from 6000 to 8000 INR per Cubic Meter for Superstructure.

Rate analysis of Brickwork excel sheet

Join our Telegram Channel to get the Rate Analysis of Brickwork in Excel Format.

Rate analysis of brickwork masonry pdf

You can download the above example from our Telegram Channel- Civilwala.org

Brick Work Labour Rate Per Cum

Calculation for Brick Work Labour Rate per CumUnitQty.RateAmount
Mason 1st Classday0.4750300
Mason 2nd Classday0.4750300
Coolieday1.43600858
Bhishtiday0.20600120
Total 1578 INR
Brick Work Labour Rate per Cum

Total Labour Cost for Brickwork, as calculated from the above example is 1578 INR, which is 1578/6957=22% of the total project cost. The Brick Work Labour Rate Per Cum is 1500-1800 INR depending on the availability of labour and the location.

How do you calculate rate analysis for brickwork?

1. Calculation of Material
(i) Calculation of Bricks = 500 Nos.x 5 =2500₹
(ii) Calculation of Cement = 1.82 bags (Cement sand ratio of 1:4) =1.82 x450 =819₹
(iii) Calculation of Sand = 0.253 Cum x1000= 253₹
2.Labour rate Calculation
(i) Mason 1st Class = 0.4 day x 750 =300₹
(ii) Mason 2nd Class= 0.4 day x 750 =300 ₹
(iii) Coolie = 1.43 day x 600 =858₹
(iv) Bhishti = 0.20 day x 0.20 = 120₹
Scaffolding LS=50₹
Add 1% water charge on total =52
Add GST =738
Add 15%CPOH=898.49₹
Add 1% cess =68.88
Total = 6957.28

How many bricks are in 1m3?

The number of Bricks in a Cum depends on the size of the brick. For brick of standard size ( 19cm x 9cmx9cm) total of 500 bricks are required for 1 cum of brickwork.

What is the percentage of mortar in brickwork?

For Converting dry volume into the required volume of mortar 33% extra is taken.

How do you calculate mortar for brickwork?

  • The volume of 1 Brick without mortar = 0.19×0.09×0.09 =0.001539 (taking standard size brick as example)Volume of Bricks in 1 cum of Brickwork = 500x 0.001539 = 0.7695Volume of Mortar= 1-0.7695 = 0.2305 CumAdd 25% extra for Dry volume of a mortar = 0.2305 Cu.m. x 1.25 = 0.288125 Cu.m.Add 10% extra for wastage = 0.288125*1.10 =0.316 Cum